Timeline

NHS Lanarkshire has undertaken a number of reviews and explored a number of options over the years.

This process to explore options for a refurbishment or replacement was formalised with the approval of an Initial Agreement in 2017. This was followed in 2023 with the approval of the Outline Business Case (OBC) for the hospital. The next key milestone for business case approval is the submission of the Full Business Case (FBC), followed by the construction of the hospital ahead of the planned opening in 2031.

Jan 2021

Wester Moffat site selection

July 2023

OBC Approval

Sept 2023

Laing O’Rourke selected as Pre-Construction Services Agreement Partner

June 2024

Approval of planning application

Sept 2024

Site Preparation Works
 (Settlement Trials)

2025

Enabling Ground Works start

2031

Hospital Opens