Timeline

University Hospital Monklands (UHM) is an ageing facility that was designed in the 1960s and constructed in the 1970s. While it reflected a good and competent design at the time, the facility is beyond its serviceable life and is in need of replacement.

NHS Lanarkshire has undertaken a number of reviews and explored a number of options over the years. This process to explore options for a refurbishment or replacement was formalised with the approval of an Initial Agreement in 2017. This was followed in 2023 with the approval of the Outline Business Case (OBC) for the hospital. The next key milestone for business case approval is the submission of the Full Business Case (FBC), followed by the construction of the hospital ahead of the planned opening in 2031.

Jan 2021

Wester Moffat site selection

July 2023

OBC Approval

Submitted Aug 2023

Application for Full Planning Permission

Sept 2023

Laing O’Rourke selected as Pre-Construction Services Agreement Partner

2025

Site Start

2031

Hospital Opens

“The new hospital at Wester Moffat in Airdrie will support our forward-thinking clinical model, and workforce planning is integral to provide safe and effective patient care across all wards and departments.”

Fiona Cowan
Clinical Lead – Nursing
Monklands Replacement Project